The Boerne ISD has been told that May 28 marks the “substantial completion” date for its Aquatics Learning Center — nine months later than the project’s original completion date.
Boerne ISD board and administration met May 5 with management from Tegrity Contractors, the firm hired in summer 2023 to build the $8.7 million facility, approved by Boerne voters in the 2022 bond election.
“We see the progression; we’re making up time. But we’re also seeing if we have any struggles,” Ramiro Gurrero, Boerne executive director of operations, told the school board at the May 5 meeting.